Acela trains delayed a year by new round of testing
The Washington Post
June 3, 2021 at 3:30 p.m. GMT+5:30 (US)
Debut of Amtrak’s new Acela trains delayed a year by new round of testing
The manufacturer had to alter designs to make the train compatible with aging infrastructure in the Northeast Corridor
Amtrak’s new Acela train cars need an extra round of testing to ensure they can safely operate on the curvy and aging tracks of the Northeast Corridor, railroad officials said, confirming a year-long delay in the delivery of the new trains.
A prototype train that began tests on the route between Washington and Boston last year was incompatible with the corridor’s track and its catenary system — the overhead wires that supply the train with electricity. The train had to be modified to work harmoniously with the infrastructure, according to Amtrak officials.
Source:
https://www.washingtonpost.com/transportation/2021/06/03/amtrak-acela-new-trains/
Recommended for you
In 2023, Deutsche Bahn will invest a record EUR 7.6 billion in Germany's Strong Rail system
21 March 2024 (Germany) Net capital expenditures from Deutsche Bahn's own funds reached a new high of almost EUR 7.6 billion, up more than 16% year over year. In 2023, demand for train passenger service kept growing. Significant advancements were also made by DB in its passenger services in 2023, including the addition of more links, a larger and more contemporary fleet of vehicles, and more digital services. Source https://www.deutschebahn.com/en/presse/press_releases/Deutsche-Bahn-invests-a-record-EUR-7-6-bn-in-Strong-Rail-in-Germany-in-2023-12760244#
23 hrs ago
Read MoreAn agreement was concluded by Stadler and GYSEV regarding the delivery of next-generation intercity EMUs.
27 March 2024 (Sopron, Hungary) GYSEV Zrt. and Stadler have inked a contract for the supply of 9+4 intercity EMUs. Beginning in 2027, the operator railway company intends to operate the cars on the lines Sopron-Budapest and Szombathely-Budapest. The new multisystem trains will be authorized to run in Austria in addition to Hungary. At Stadler's carbodies center of excellence in Szolnok, Hungarian experts will fabricate the aluminum bodyshells for the five-car trainsets. Source https://www.stadlerrail.com/media/pdf/20240327_gysev_ic_eng.pdf
yesterday
Read MoreSiemens Mobility and Canadian operator Metrolinx have been awarded a new service contract
27 March 2024 (Canada) For the Central Region of Toronto's passenger railway infrastructure system, Siemens Mobility has been selected by Metrolinx, the regional public transit operator for the Greater Toronto and Hamilton Area, to manage track, signal, and right-of-way maintenance. Siemens Mobility already provides signal and communications services at the Metrolinx Network Operations Center, as well as maintenance services in the West Region, which this agreement expands upon. For almost 40 years, Siemens Mobility has been offering transportation industry solutions in Canada. Source https://press.siemens.com/global/en/pressrelease/siemens-mobility-awarded-further-service-contract-canadian-operator-metrolinx
yesterday
Read More