UAE: Etihad Rail completes excavation works of 9 tunnels

Khaleej Times 
21 Nov 2021 (UAE) 

The 6.9-km stretch of tunnels are being constructed across Fujairah and Ras Al Khaimah

Etihad Rail, the UAE’s national rail network, on Sunday said it had completed excavation work on all nine tunnels of the Package D of Stage Two ahead of its schedule and the work on the project is proceeding according to schedule.

His Highness Sheikh Hamad bin Mohammed Al Sharqi, Member of the Supreme Council and Ruler of Fujairah, and Sheikh Mohammed bin Hamad Al Sharqi, Crown Prince of Fujairah, visited the Sakamkam area in Fujairah, in the presence of Sheikh Theyab bin Mohamed bin Zayed Al Nahyan, Chairman of Etihad Rail, to announce the completion of excavation works of all the nine tunnels extending over 6.9 kilometres.

The tunnels are being constructed across Fujairah and Ras Al Khaimah as part of Package D of Stage Two, two months ahead of schedule.

The completion of the excavation of the nine tunnels recorded one million working hours. The project was supervised and carried out by more than 600 experts, specialists, and workers using the latest tunnelling machinery and modern technologies.