The MRTA trains consultants. Observe the test findings intently. to evaluate the plan's appropriateness and readiness. Maximum safety and convenience of access to public services should be considered.

At the end of August 2023, the Mass Rapid Transit Authority of Thailand (MRTA) reported that the Khae Rai–Min Buri section of the Pink Line Project was proceeding as expected.

Civil works progress was 96.71%, M&E electric railway systems progress was 98.35%, and overall progress was 98.03%.