For the engineers of Delhi Metro, bringing the Airport Express Link's operational speed up to 100 KMPH posed a significant engineering task.
The key accomplishments of this enormous endeavour included careful planning, 24-hour supervision, and a determination to avoid having the work interfere with passenger operations.
One of the most difficult technological developments in the country's annals of Metro train operations will be this.
The goal was only reached within six months, far ahead of the anticipated deadlines, thanks to a detailed mechanism for the replacement of some rail components,
maintenance and repair of civil structures, and re-profiling of some Rolling stock components.
The increase in operational speed required numerous track-related maintenance tasks to ensure that passengers would experience the least amount of inconvenience possible,
making it a historic technical development in Metro train operations.
In order to make them more compatible with the revised speed strength, the main activity included replacing more than 2.6 lakh existing tension clamps on the rails throughout the complete AEL network with high-frequency tension clamps.
Source
https://www.delhimetrorail.com/pages/en/pressrelease_details/increasing-to-100-kmph-a-major-challenge-for-delhi
Recommended for you
The UAE-Oman Railway Link (Hafeet Rail) signaling contract is won by Siemens Mobility and Hassan Allam Construction
24 April 2024 (UAE) The 303-kilometer project is the first cross-country undertaking in the Middle East and Arab World, linking the capital city of Abu Dhabi, United Arab Emirates, with Sohar, Sultanate of Oman. The network's Oman segment is the Sultanate of Oman's first-ever railway system delivery. Over the 303-kilometer Abu Dhabi – Sohar railway link, Siemens Mobility and Hassan Allam Construction will provide the design, construction, and integration of the ETCS Level 2 signaling, telecom, and power supply systems. Source https://press.siemens.com/global/en/pressrelease/siemens-mobility-together-hassan-allam-construction-wins-signaling-contract-uae-oman
2 days ago
Read MoreIn order to modernize the Portuguese railway infrastructure, Thales secures three major contracts
18 April 2024 (Portugal) Together with partners SISINT and CONECTICABO, Thales has successfully negotiated three large contracts worth over 10 million euros to upgrade the mainline railway in Portugal. The Portuguese mainline railway infrastructure's quality, safety, and operation will all be considerably raised by these projects. With many successful signaling system renewal contracts under its belt, Thales is well-positioned to be a major player in the overall modernization of the telecom network. Source https://www.thalesgroup.com/en/worldwide/transport/press_release/thales-secures-three-major-contracts-modernize-portuguese-railway
2 days ago
Read MoreThe first anniversary of the China-Laos international passenger train's inaugural operation
15 April 2024 (China) The first anniversary of the China-Laos international passenger train's operation was celebrated on April 13. All told, the train has carried 700,000 passengers, 180,000 of whom were cross-border travelers from 87 different nations and regions. The operation is secure, steady, and well-organized, with a 100% departure and 99% arrival on-time percentage, respectively. Source https://www.crrcgc.cc/en/g7389/s10408/t347740.aspx Picture Courtesy http://english.scio.gov.cn/beltandroad/2023-04/13/content_85226948.htm
3 days ago
Read More